Earned Value Management theory and its application on practice at

Download Report

Transcript Earned Value Management theory and its application on practice at

Dmitry Kekelidze Software Engineer JINR – LIT/ CERN - GS-AIS

   EVMS concepts NICA project EVM web-based application

EVM is the project management tool...

Are we there yet?

How much longer before we’ve arrived?

What can we do about it?

performance measurement

how am I doing against my baseline plan?

performance management

what do I need to do to bring the project in on cost and schedule?

   • • Preparation

Research Topic Decide on Structure

• • • • Make Slides

EVM Basics EVM Advanced NICA Intro Conclusion

• • Finishing up

Trial Presentation Implement Feedback

cost Research Presentation template

Start slides

EVM Basics EVM Advanced Agenda Conclusion NICA Intro

Slides ready

Reshuffle Dry run time

What is an honest measure for what is achieved?

Research Presentation template

Start slides

EVM Basics EVM Advanced Agenda Conclusion NICA Intro cost

Slides ready

Reshuffle Dry run time

Main metrics :

PV

- Planned Value

EV

- Earned Value

AC

- Actual Cost The portion of work expected to be completed at a given date, times the authorized budget allocated to carry out that work The value of completed work expressed in terms of the budget assigned to that work The costs actually incurred and recorded in accomplishing the work performed

Budget Planned Value Cost Actual Cost now •Are we ahead or behind schedule?

•Are you getting value for money?

•Did you spend money on the right things?

Achievement Earned Value time

Underspending but ...

Planned Value now Actual Cost Earned Value time

Underspending but ...

now Planned Value Earned Value Actual Cost time

BAC

: Budget At Complete

PMR

Project Management Reserve project start

PV AC EV

now

CV = EV – AC

Cost Variance

SV = EV – PV

Schedule Variance project end SV < 0 SV > 0 CV < 0 CV > 0 time

Schedule Variance SV = EV–PV Schedule Performance Index Cost Variance SPI = EV/PV CV = EV-AC Cost Performance Index CPI = EV/AC Estimate At Completion To Complete Performance Index EAC = BAC / CPI TCPI BAC AC) = (BAC-EV)/(BAC In currency. Negative means delay < 1 means delay In currency. Negative means overcost.

< 1 means overcost Forecast final cost Can we catch up?

now time EAC

     

Requires development of integrated baseline

Results in better project definition and planning

Early identification of trends and problems Accurate picture of project status

Cost, schedule, and technical segregation of schedule and cost variances

Projection of final costs Project control by the team

Enables project manager to make informed decisions based on facts

Results in successful projects

On time, on cost

Requirement 100h Architecture 100h 100h Design 200h Code 100h Testing

Task

Requirements (100h)

Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Status at end of Month 5

S------F Complete, Spent 100h Architecture (100h) S----PF --F Complete, Spent 120h Design (100h) Code (200h) Testing (100h) PS-S-PF --F PS----S -----PF PS---PF Complete, Spent 125h 25% Complete, Spent 70h Not yet started

At the end of Month 5, what is?

Calculation

PV 100 + 100 + 100 + 200 EV AC BAC CV CPI SV SPI IEAC TCPI 100 + 100 + 100 + 50 100 + 120 + 125 + 70 100 + 100 + 100 + 200 + 100 350 - 415 350 / 415 350 - 500 35,000 / 50,000 600/0.84

(600-350)/(600-415)

Answer

500h 350h 415h 600h -65h 84% -150h 70% 711h 135%

WBS

: Work Breakdown Structure, hierarchical list of all the activities to be performed to complete the project.

Workunits

: The “Leaves” of the WBS tree. Activity small in size/duration, under responsibility of one person.

 Workunits use

Resources

(money, people) to produce

Deliverables

EVM suitable for projects that have:

• Clear definition of work scope • Project schedule range from a few months to many years • Small to very large cost

• Technically complex and demanding, i.e. that cannot be fully specified in the front end phase; • Long makespan: economic effects like inflation • Involving many contributors, contractors, suppliers... i.e. many activities that are outsourced, result oriented.

   EVMS concepts NICA project EVM web-based application

Is NICA large-scale project?

   

Work planned for period from year 2012 till 2017 Estimated cost is more than 100M $ Tasks to complete:

• General Infrastructure • Accelerator • MPD Detector

All the work have to be well coordinated

18% overspend

announcement … only  Technical Coordinator →

“the project is behind schedule”

  Project Administrator →

“the project is under-running”

LHC Team: not is position to demonstrate that the project could be completed within allocated budget!

Member States asked the LHC Project Management to set up a formal Project Control System

EVM-based

project control system 

Deliverable-oriented

physical progress monitoring  Interfaced to

accounting systems

, to get accurate information on actual costs  Excel spreadsheets to interact with DBs 

Web-based

An activity of the project

Activity not started Progress

0%

Activity half-way Progress

50%

Activity completed?

90%-syndrome

 • • •

Re-established trust

Cost and Schedule Review Committee: ‘world class’ CERN management was formally congratulated by Member States Further overruns were discussed in the context of proven project control.

Project culture at CERN and cost awareness of project engineers have improved.

   EVMS concepts NICA project EVM web-based application

WBS • Web interface • Excel files Workunits Resources  Personnel  Material Deliverables

Reminders for progress reporting

 Crosstab to drill drown through the WBS structure (or other dimension…)  PV, EV, AC Charts at every WBS level

 Objectively measures performance of the project as it moves from project initiation through project closure.

 Provides early warning of potential project adverse performance.

 Shows Opportunity associated with positive schedule variance .  Enables the management of risk associated with underwriting or insuring against negative schedule variance .

 Provides a means to forecast future performance based upon past performance.

Спасибо!

Dmitry.Kekelidze@cern.ch

Questions?