Transcript Slayt 1

REGIONAL COMPETITIVENESS
OPERATIONAL PROGRAMME
7TH SECTORAL MONITORING COMMITTEE
MEETING
14 October 2010 – Ankara
Draft Agenda
For the Seventh Sectoral Monitoring Committee Meeting
For the Regional Competitiveness Operational Programme in Turkey
(14 October 2010, 09:30 / MoIT)
1. Opening statements – by the Head of the Operating Structure, and by the Commission (HoS +
EC)
2. Approval of the Minutes of the last meeting (HoS + EC)
3. Approval of the agenda of the Sectoral Monitoring Committee Meeting (HoS + EC)
4. Information on the activities of the Audit Authority in the preparation of the Annual Audit Activity
Report for the RCOP (Audit Authority)
5. Information on state of play in first package of strategic projects (OS)
6. Information on state of play in second project package (OS)
7. Information on state of play in Measure 1.2 (financial engineering) (OS)
8. Information on Monitoring Report and Monitoring Sheets (OS)
9. Information on absorption (n+3), procurement plans and disbursement forecasts (OS)
10. Information on technical assistance activities (OS)
11. Information on new institutional set-up and preparations for Accreditation of Finance and
Contracts Unit in RCP CIC (OS)
12. Information on the implementation of the Communication Action Plan (OS)
13. Information on the adoption of the modifying decision for the revisions and extension of the
Operational Program and on the revision of the Financing Agreement, information on supplementary
advance payment (EC)
14. Information on the preparation of mid-term evaluation (HoS + Strategic Coordinator + NIPAC +
EC)
15. Indicative date for the next Sectoral Monitoring Committee (HoS + EC)
16. AOB
STATE OF PLAY IN FIRST PACKAGE OF
STRATEGIC PROJECTS
1st PROJECT PACKAGE
1st Project Package consists of 10 projects of the following Beneficiaries:
• KOSGEB, Small and Medium Enterprises Development Organization
• TUBITAK, The Scientific and Technological Research Council of Turkey
• MoIT-DG for R&D, Ministry of Industry and Trade DG for Industrial Research and
Development (3 projects)
• MoCT, Ministry of Culture and Tourism
• TOBB, The Union of Chambers and Commodity Exchanges of Turkey
• UoFT, Undersecretariat of the Prime Ministry for Foreign Trade
• MoIT – RCP-CIC, Technical Assistance + Publicity
1st PROJECT PACKAGE
Under 10 projects, there are 32 contracts :
From the 1st Project Package:
-19 Forecast Notice Published
-8 Procurement Notice Published
-1 Framework Contract awarded
-3 Contracts will be signed until the end of 2010.
-8 Contracts are expected to be signed within 2011.
1st Project Package
Priority Axes 1:Improvement of Business Environment
01- Establishment of Business Incubators and Development of a Network
among Incubators in Turkey (Kastamonu, Malatya, Tokat)
Beneficiary: KOSGEB
Type of
Contract
(Budget €)
Date of
Submission to
CFCU
Indicative
Publication Date of
Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
The Forecast Notice for the Works was published on
14 July 2009.
Works
(8.487.392)
Service
(Supervision)
(939.500)
March 2010
November 2010
June 2011
The tender dossier has been sent to the EUD for exante approval in late September, 2010. The
Procurement Notice (PN) is expected to be
published in the middle of November 2010.
The Procurement Notice for the Supervision was
published on 03 August 2010.
March 2010
Published
(03.08.2010)
June 2011
The tender evaluation has been going on and ShortList Notice is expected to be published in the middle
of November.
1st Project Package
Priority Axes 1:Improvement of Business Environment
01- Establishment of Business Incubators and Development of a Network
among Incubators in Turkey (Kastamonu, Malatya, Tokat)
Beneficiary: KOSGEB
Type of
Contract
(Budget €)
Date of
Submission to
CFCU
Indicative
Publication Date of
Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
Technical
Assistance
(Institutional
Building)
(4.000.000)
The First Quarter
of 2011
The Third Quarter
of 2011
The First Quarter
of 2012
The OIS document has been approved by the EUD in
June 2010 and the ToR document will be submitted
to the CFCU in January 2011.
Supply
(195.000)
The First Quarter
of 2011
The Third Quarter
of 2011
The First Quarter
of 2012
The OIS document has been approved by the EUD in
June 2010 and the ToR document will be submitted
to the CFCU in the first quarter of 2011.
1st Project Package
Priority Axes 1:Improvement of Business Environment
02- Establishment of Innovation Centre For Food – INNOFOOD CENTER (Kocaeli,
G.Antep, Şanlıurfa, Giresun)
Beneficiary: TÜBİTAK
Type of Contract
(Budget €)
Technical Assistance
(Institutional Building)
(1.978.350)
Date of Submission
to CFCU
(indicative)
The First Quarter of
2011
Publication Date
of Procurement
Notice
(indicative)
The Third Quarter
of 2011
Date for signature
of Contract
(indicative)
The First Quarter of
2012
State of Play
In February 2010, the Major Project
Application Form was submitted to
the Commission.
The admissibility letter from the
Commission has been received.
Works
(2.387.000)
The Third Quarter of
2011
The First Quarter
of 2012
The Third Quarter
of 2012
The first comments of the
Commission has not been received
yet.
Service (Supervision)
(143.220)
The Second Quarter
of 2011
The Fourth
Quarter of 2011
The Second Quarter
of 2012
According to the comments of the
Commission, the Major Application
Form, Feasibility Report and CostBenefit Analysis of the project will
be revised.
Supply
(16.033.683)
The Third Quarter of
2011
The Second
Quarter of 2012
The Fourth Quarter
of 2012
The procurement plan for this
project will be prepared accordingly
and more accurately.
1st Project Package
Priority Axes 1:Improvement of Business Environment
03-04-05-TECHNOLOGY DEVELOPMENT ZONES (Gaziantep, Kayseri, Elazığ)
Beneficiary: MoIT, DG for R&D
Type of Contract
(Budget €)
Date of
Submission to
CFCU
Indicative
Publication Date
of Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
There will be 3 separate tenders for each TDZ.
The Forecast Notices for the Service were published
on 9th and 24th of June 2009.
Technical Assistance
(Institutional Building)
(2.095.750 Gaziantep)
(1.215.176 Kayseri)
(1.116.860 Elazığ)
April 2009
November
2010
October 2011
The last revision of the TA tender documents was
submitted to the CFCU in the beginning of this month.
The revised OIS document is going to be submitted to
the EUD within this month by the CFCU.
Supply
(1.471.405 Gaziantep)
(553.970 Kayseri)
(521.000 Elazığ)
April 2009
The first
quarter of
2011
May 2011
The technical documents (Supply TS and Market
Research) of the Technology Development Zones
(TDZs) for Supply were merged in one Supply TS
document upon the CFCU’s recommendation.
The Tender Dossier is under examination of the CFCU
and their comments are expected in the near future.
1st Project Package
Priority Axes 1:Improvement of Business Environment
03-04-05-TECHNOLOGY DEVELOPMENT ZONES (Gaziantep, Kayseri, Elazığ)
Beneficiary: MoIT, DG for R&D
Type of Contract
(Budget €)
Date of
Submission to
CFCU
Publication Date
of Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
The technical documents of the Technology Development
Zones (TDZs) for Works were merged in one Works TS
document.
Works
(3.848.294 Gaziantep)
(5.601.131 Kayseri)
(4.764.826 Elazığ)
April 2009
Published
(07.08.2010)
March 2011
The PN has been published on 7th of August, 2010. The
deadline for submission of tenders is on 23rd of
November, 2010.
The first site visits in the framework of tender evaluation
has been paid on 11th of October to Elazig TDZ and all
the site visits will be completed within this month.
Service (Supervision)
(366.000 Gaziantep)
(454.500 Kayseri)
(366.000 Elazığ)
The PN has been published in the beginning of May,
2010.
April 2009
Published
(10.05.2010)
May 2011
The tender evaluation process has been going on; the
Short-List Notice is expected to be published in the
beginning of November, 2010.
1st Project Package
Priority Axes 1:Improvement of Business Environment
06-Winter Tourism Corridor in Erzurum, Erzincan and Kars
Beneficiary: Ministry of Culture and Tourism (MoCT)
Type of
Contract
(Budget €)
Date of
Submission to
CFCU
(Indicative )
Publication Date of
Procurement
Notice
(Indicative )
Indicative Date
for signature of
Contract
(Indicative )
Technical
Assistance
(Institutional
Building)
(1.876.000)
The First Quarter
of 2011
The Third Quarter of
2011
The First Quarter
of 2012
Works
(5.492.033)
The First Quarter
of 2011
The Third Quarter of
2011
The First Quarter
of 2012
Technical
Assistance
(Supervision)
(720.500)
The First Quarter
of 2011
The Third Quarter of
2011
The First Quarter
of 2012
Supply
(101.377)
The First Quarter
of 2011
The Third Quarter of
2011
The First Quarter
of 2012
State of Play
The comments from the EUD for the OIS document,
Feasibility Report, Cost-Benefit Analysis and
Environmental Impact Analysis have been received
in April 2010. All the documents have been revised
accordingly; but the single absent document of the
programming stage is the results of drinking water
analysis for Erzincan-Ergan Region, which
is
expected to be submitted by the MoCT within this
month. According to those results, either the
concerned documents are again going to be
submitted to the EUD or the project design is going
to be discussed to come up with the solution by all
parties.
The MoCT has already sent the tender documents
for works and TA and the MoIT examined the
documents twice and the documents are ready to
be submitted to the CFCU provided that the
programming stage finalized soon.
1st Project Package
Priority Axes 2: Strengthening of Enterprise Capacity and Foster Entrepreneurship
07- Enlargement of the European Turkish Business Centres Network to Sivas,
Antakya, Batman, Van
Beneficiary: TOBB
Type of
Contract
(Budget €)
Date of
Submission to
CFCU
Publication Date
of Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
Technical
Assistance
(Institutional
Building)
(7.500.000)
31 March 2009
Published
21.01.2010
January 2011
The contract signature is expected to be finalized in
November, 2010.
Supply
(600.000)
31 March 2009
Published
19.05.2010
November 2010
Supply
(400.000)
The First/Second
Quarterof 2011
December 2011
(indicative)
May 2012
The contract signature is expected to be finalized in
November, 2010.
TS will be prepared in further phases.
1st Project Package
Priority Axes 2: Strengthening of Enterprise Capacity and Foster Entrepreneurship
08-Strengthening of SMEs for Networking and Regional Cooperation (Samsun,
Trabzon, Gaziantep, Kahramanmaraş, Çorum)
Beneficiary: UFT
Type of
Contract
(Budget €)
Date of
Submission to
CFCU
Publication Date of
Procurement
Notice
Indicative Date
for signature of
Contract
State of Play
Technical
Assistance
(Institutional
Building)
(3.500.000)
31 March 2009
Published
04.02.2010
November 2010
The contract signature is expected to be finalized
in November, 2010
The First PN and TD were published in March
2010, but the tender was cancelled by the CFCU.
The second PN has been published in August this
year and the deadline for submission of tenders is
1st of November, 2010. The contract signature
date is expected to be in January 2011.
Supply
(500.000)
31 March 2009
Published
18.08.2010
January 2011
Supply
(300.000 )
The Third Quarter
of 2011
(indicative)
The First Quarter of
2012
(indicative)
The Third Quarter
of 2012
(indicative)
Supply
(700.000)
The First Quarter
of 2012
(indicative)
The Third Quarter of
2012
(indicative)
The First Quarter
of 2013
(indicative)
Tender documents will be prepared in further
phases.
STATE OF PLAY IN SECOND PROJECT
PACKAGE
SECOND PACKAGE OF PROJECTS
PROGRESS OR NOT?
Timelines and Methodology of UNDP Technical Cooperation (TC) Project
Submission of 9 OIS
Rejection of 6 OISs by EUD
Site visits
Submission of 6 OISs to
EUD for Final Approval
Extension of UNDP
TC Project
Mid-Term Review
Meetings
Submission of First
Draft Reports
Trilateral Kickoff Meetings
Site visits
Identification of Sector
Specific Experts within
the UNDP TC Project
June 2010
July 2010
August 2010
September 2010
October 2010
SECOND PACKAGE OF PROJECTS
PROGRESS OR NOT?
Timelines and Methodology of UNDP Technical Cooperation (TC) Project
Handover-Takeover Process
(UNDP TC Project – RCOP
TA Project)
Finalization of 6 OISs
Identification of Operations
subject to RCOP-Technical
Assistance (TA) Operation
Finalisation of 11-13 OISs
Finalization of 8 OISs
November 2010
Finalization of 9
OISs
December
2010
January 2011
February 2011
FACTOR
Amendment of IPA Implementing
Regulation
Delay in the operationalisation of
UNDP TC Project
Different and complex approaches
for the operations under Measure 1.4
Comprehensive list of annexes and
supporting documents of OIS
Difficulty at designing and
diversifying TA components of OISs.
Overlap with previous EU supported
operations
Low capacity of beneficiaries and
slow reaction timeline
Lack of human resource capacity of
whole IPA system
DELAY? YES
SOLUTION
Finalized by trilateral consultation
Multi-lateral consultation and
settlement
Still under discussion
Simplify and standardise the
preperation methodology of relevant
documents.
Identification of necessary generic
activities
Exclusion of similar activities
Continuously inform
Increase the number of RCP-CIC staff
NEED FOR RE-EVALUATION OF OPERATIONS UNDER NEW
CONDITIONS
RE- EVALUATION OF MATURITY OR LEVEL OF PROGRESS
Concept
Complexity of
Components
MATURE
CONSIDERABLY
PROGRESSED
PROGRESSED
Scale&
Sustainability
Technical
Preparations
RE-EVALUATION
METHODOLOGY
LESS
PROGRESSED
UNDER
DISCUSSION
• 20%
67 M.€
• 18%
44 M.€
• 20%
47M.€
• 13%
27 M.€
• 29%
20 M.€
LEVEL OF
PROGRESS
ABSORPTION
(Indicative)
STATE OF PLAY IN MEASURE 1.2
MEASURE 1.2
FINANCIAL ENGINEERING INSTRUMENTS
PROJECT 1: GREATER ANATOLIA GUARANTEE FACILITY (GAGF)
Official
Application
(MoIT)
No objection letter
(EC – DG Regio)
Official Approval
Letter (EUD)
• 19 April 2010
• 11 May 2010
Launch Event
Ankara
Transfer of funds
to EIF Accounts
• 16 July 2010
• 9 August 2010
Signing Ceremony
with Intermediary
Banks
• 22 March 2010
• 22 October 2010
MEASURE 1.2
FINANCIAL ENGINEERING INSTRUMENTS
PROJECT 1: GREATER ANATOLIA GUARANTEE FACILITY (GAGF)
st
1
Pillar
•
•
•
•
Credit Guarantee
1.500 micro enterprises (25.000 €)
EIF-KGF Partnership
5 mil.€
2nd Pillar
• Credit by risk sharing
• 25 mil.€ leverage
• 2.500 SMEs (200.000€)
• 5 intermediate banks (IB) (250 mil.€)
• EIB (250 mil.€)
• IPA-EIB-IB partnership
• 500 mil.€ credit volume
rd
3
•
•
•
•
Pillar
Contribution to KGF capacity building
Technical assistance to IB-MoIT
Publicity&promotional activites
2 mil.€
MEASURE 1.2
FINANCIAL ENGINEERING INSTRUMENTS
PROJECT 2: GAP (Southeastern Anatolia Project) Venture Capital (GAP-VC)
Official Application
of Beneficiary
(KOSGEB)
• 12 October 2010
Official Application
of MoIT
Last Quarter of
October (Tentative)
KOSGEB-IVCI-EIF
Partnership
16 mil.€
75% of total budget
dedicated to GAP
Region
7-9 investment
Launch of project
first quarter of 2011
at the latest
ABSORPTION CAPACITY (N+3)
AND DISBURSEMENT FORECASTS
ALLOCATED BUDGET FOR RCOP
Year
EU
Contribution
(EUR)
National
Contribution
(EUR)
Total EUR
2007
41.900.000
7.394.118
49.294.118
2008
43.500.000
7.676.471
51.176.471
2009
54.800.000
9.670.588
64.470.588
2010
71.430.000
12.605.294
84.035.294
2011
88.020.000
15.532.941
103.552.941
TOTAL
299.650.000
52.879.412
352.529.412
TOTAL BUDGET OF THE PACKAGES
Package
Number
of the
projects
EU Contribution
(EUR)
National
Contribution
(EUR)
First Project
Package
(%85-%15)
10
75.999.005
13.411.589
89.410.594
Second Project
Package
(%82-%18)*
44
168.100.000
36.900.000
205.000.000
Third Project
Package
(%85-%15)
2
40.800.000
7.200.000
48.000.000
TOTAL
56
284.899.005
57.511.589
342.410.594
* Average of the sustainability analysis of several projects in second package
Total EUR
DISBURSEMENT FORECAST AND N+3 GAP
Expenditure Estimations (EU Contribution)
2010
2011
2012
2.151.195
36.119.868
30.541.523
7.018.259
168.160
75.999.005
0
3.936.000
117.342.000
35.588.000
11.234.000
168.100.000
Third Package
(Mea.1.2)
27.200.000
13.600.000
0
0
0
40.800.000
TOTAL (per
year)
29.351.195
53.655.868
147.883.522
42.606.259
11.402.160
284.899.005
First Package
Second
Package
TOTAL
(cumulative)
N+3
Expenditure
Requirements
Expenditure paid
and declared*
(A.P. 64.275.000)
N+3 Gap
(cumulative)
29.351.195
41.900.000
-22.375.000
6.976.195
83.007.063
43.500.000
21.125.000
61.882.063
2013
230.890.586
54.800.000
75.925.000
154.965.586
*Figures also include the advance payment which is equal to 64.275.000€ .
**It should be paid and declared to the EC by the end of 2017.
2014
273.496.845
71.430.000
147.355.000
126.141.845
TOTAL
284.899.005
88.020.000
235.375.000
49.524.005
284.899.005
299.650.000
299.650.000
-14.750.995
INFORMATION ON
TECHNICAL ASSISTANCE (TA)
ACTIVITIES
TA Operation (2007 TR 16I PO 003. 3.1. 01)
Components of the Operation
Component 1 – Capacity building in programme and
project level: training and support in management
and implementation functions to the RCP – CIC and
final recipients
Corresponding Contract
Budget
(Euro)
Service contract 1
TR07R3.01-01Technical Assistance on Institutional
Building for the Implementation of RCOP
6.770.000
Component 3 – Establishment of the MIS System
within the RCP-CIC
Service contract 1
TR07R3.01-02Technical Assistance on MIS for the
Implementation of RCOP
1.743.500
Component 4 – Supply component
Supply contract
TR07R3.01-10Supply of IT Equipment for
Management Information System
Component 2 – Supporting the establishment of the
RCP – CIC Finance and Contracts Department (FCD)
Component 5 – Support for programme and
operations monitoring and implementation (lumpsum)
Direct contract
Lump-sum covering of the per-diem, transportation
and accommodation charges of experts and staff who
are on mission)
Component 6- Framework contracts (lump-sum)
FWC 1
(Road map for the Establishment of the FCD within
RCP-CIC)
FWC2
(Study for Compliance Assessment Audit of MoIT)
251.310
200.000
400.000
GRAND TOTAL
9.364.810
TA Operation (2007 TR 16I PO 003. 3.1. 01)
Contracts
State of Play
• The P/N published on 29th of
1
TR07R3.01-01
2
TR07R3.01-02
Technical Assistance on
Institutional Building for the
Implementation of RCOP
Jan. 2010 and the tender
evaluation process was launched.
• Short list notice was published
on 4th of June 2010.
•Evaluation of technical offers
has been completed by the
Evaluation Committee (second
half of September 2010)
• The expected date for the
official commencement of this
operation is November 2010.
Forecast Notice published on
Technical Assistance on MIS for 04.06.2009. ToR is revised by MoIT
the Implementation of RCOP
and sent to CFCU on 6th July 2010
TA Operation (2007 TR 16I PO 003. 3.1. 01)
Contracts
3
TR07R3.01-10
Supply of IT Equipment for
Management Information
System
4
TR07R3.01-03
5
TR07R3.01-07
Direct contract
FWC (Road map for the
Establishment of the FCD
within RCP-CIC)
State of Play
Forecast Notice published on
04.06.2009. TS is revised by MoIT
and sent to CFCU on 6th July 2010
•has been awarded on 24.06.2010
with a budget of 116.818€
•implementation has been
launched in the beginning of July
2010.
• to be finalised by November
2010
FWC (Study for Compliance ToR is prepared and sent to CFCU on
Assessment Audit of MoIT) 28 Sept. 2010 by MoIT
An official letter sent to DG REGIO on 13th July 2010 asking for an
instruction note defining the methodology to sign a direct grant
contract
Other TA Activities
MATRA Project (Support to MoIT for the proper
implementation of the RCOP (G2G EVD Project))
 Finalised in June 2010. Final Report is submitted to RCP-CIC.
UNDP TC (for reviewing and revision of OIS for 2nd
project package)
 Ongoing.
NEW INSTITUTIONAL SET-UP AND
PREPERATIONS FOR ACCREDITATION OF
FINANCE AND CONTRACTS DEPARTMENT
UNDER RCP-CIC
REGIONAL COMPETITIVENESS PROGRAMME COORDINATION AND IMPLEMENTATION CENTER
Programming Division
Programming
Department
TA&HR Division
10
33
Head of Center
Head of Operating
Structure (HOS)
Deputy
Undersecretary
Publicity Division
Technical
Implementation
Department
Quality Assurance and
Control Department
Planning Division
10
Implementation Division
Control Division
3
Risk Management Division
Monitoring and
Evaluation
Department
Monitoring Division
Finance and Contracts
Department
Finance Division
3
Evaluation Division
Contracts Division
9
FINANCE AND CONTRACTS DEPARTMENT
FINANCE AND CONTRACTS DEPARTMENT
According to the New Agreement with CFCU, the delegated tasks will
be taken on board gradually.
FINANCE AND CONTRACTS DEPARTMENT
Activities for Capacity Building under FCD
FwC Contract
Under the ongoing FwC Contract
a Road Map Document for the
establishment of a Finance and
Contracts Department under
RCP-CIC will be prepared.
Service Contract for Capacity
Building under RCP-CIC
Not only under FCD but under the
whole RCP-CIC,
Training of recruited staff and
capacity building for taking back and
conducting the tasks delegated to
CFCU.
MIS Service Contract
MIS Suply Contract
The design of Tendering, Finance,
and Accounting Modules under
the Management Information
System.
The establishment of IT Infrastructure
of FCD and suply of required
hardware and software.
FINANCE AND CONTRACTS DEPARTMENT
Work Load of FCD in terms of Project and Contract Numbers
Number of Projects
Resp.
Inst.
CFCU
FCD
RCPCIC
Number of Contracts
1. Pack.
2. Pack.
3. Pack.
TOTAL
1. Pack.
2. Pack.
3. Pack.
TOTAL
10
13
2
25
32
52
(Appr.)
2
86
(Appr.)
-
31
-
31
-
124
(Appr.)
-
124
(Appr.)
* Following April 2012
FINANCE AND CONTRACTS DEPARTMENT
Spatial Needs
Taking the fact that the tendering, contracting, payment and
accounting procedures of totally 124 contracts will be carried out by
the FCD following April 2012 in to account … ;
Totally 7 Rooms for Tendering and 10 Rooms for office is needed.
FINANCE AND CONTRACTS DEPARTMENT
ACTION PLAN FOR THE ESTABLISHMENT OF FCD UNDER RCP-CIC
2011
January February
Action
Compliance Assesment
MoIT
TA
Submission of the ToR to the CFCU
MoIT
Submission of the FwC ToR to the
EU Delegation after the Revision
CFCU
Preperations and the Publication of
the Tender
CFCU
Tender Process and the Signature
of the Contract
CFCU
Preperation and submission of draft
Assesment Report
TA
Preperation and submission of final
Assesment Report
April
May
June
July
August
Sept.
October
Nov.
Dec.
January February
March
April
Resp.
1
Application to NAO for
Accreditation
March
2012
TA
Implementation of the Assesment
Findings
MoIT
NAO Akrediatasyonu
NAO
Application to EC for
Accreditation
NAU
Assesment of the EC
EC
Submission of the Draft Report
EC
Submission of the Final Report
EC
Conferral of Management to the
Ministry
EC
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
THANK YOU FOR YOUR ATTENTION
Ministry of Industry and Trade
Regional Competitiveness Programme
Coordination and Implementation Centre
e-mail: ipa@sanayi.gov.tr
Web adress: ipaweb.sanayi.gov.tr
ipa.stb.gov.tr