View of project site and analysis
Download
Report
Transcript View of project site and analysis
General Presentation Footer
CCS Alum Crest / Clearbrook 6-12 School
Community Presentation
12-02-2010
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Core Team Members
• Columbus City Schools
Mary Ey, Executive Director of Education Services/Resources
Susan Fossmeyer, Regional Executive Director
Doug Swartz, Project Manager
Teresa McGurr, Principal of Alum Crest High School
Nancy Vallette, Assistant Principal of Alum Crest High School
Gilda Taylor, Principal of Clearbrook Middle School
Don Cantrell, Assistant Principal of Clearbrook Middle School
• Ohio School Facilities Commission (OSFC) – Financial Partner
Rhonda Hagemeyer
• Smoot Elford Resource (SER) – Construction Manager
Bob Hurley, Superintendent
Corey Holben, Project Engineer
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Core Team Members
• Design Team
DesignGroup - Architect
Keith DeVoe
Jocelyn Krosky
Kinzelman Kline Gossman – Landscape Architect
Michael Pistiolas
Shelley Metz Baumann Hawk – Structural Engineer
EMH&T – Civil Engineer
Dynamix Engineering Ltd. – Mechanical, Electrical, Plumbing, Fire
Protection, Technology
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Schedule
• Design
July 2010 through August 2011
• Bidding
August 2011 through November 2011
• Construction
January 2012 through June 2013
• Start of School
August 2013
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
What has Occurred So Far
• Geothermal Testing
• Archeological Study
• Environmental Studies – Phase I & II
• Geotechnical Services
a. Soil borings start in December 2010.
b. Geotechnical Company will be onsite for approximately a week with their
equipment.
c. Soil samples help determine the bearing capacity of the soil for the new
building.
d. All soil borings will be back-filled onsite by Geotech Company.
• Program of Requirements
a. Design team, CCS, and schools have reconciled the program for the project.
b. Basic massing studies of the building.
c. Site Analysis.
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Project Parameters
• New 6-12 School for 250 students.
a.
b.
100 Middle School Students
150 High School Students
• Room Types:
a.
b.
c.
d.
e.
f.
g.
h.
Classrooms (Academic, Science, Computer, Wood Shop)
Cafeteria and Kitchen
Stage
Gymnasium
Media Center
Vocal & Instrumental Rooms
Art Rooms
Administration Offices
• 72,549 gross square feet.
• $13.5 million construction budget.
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Program Graphic
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Project Site
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Site Analysis
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Building Massing Study 1
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Building Massing Study 2
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
CCS Website
Alum Crest/Clearbrook Homepage
• Follow the Progress of the new school.
• Download presentations to community.
Go to:
www.columbus.k12.oh.us
a.
b.
In the bottom left-hand corner of the screen, click on ‘New Facilities’.
Under the heading ‘Learning Continues During Construction and Renovation’ click
‘more’.
c. Then, click on the heading ‘Alum Crest/Clearbrook 6-12’.
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010
Next Steps
• Schematic Design Approval with CCS and SER:
November 2010 – January 2011
• Review Schematic Design with Community:
January 2011 – Meeting Date TBD
• Design Development with CCS:
January - February 2011
• Review Design Development with Community:
March 2011 – Meeting Date TBD
Columbus City Schools
Alum Crest / Clearbrook 6-12 School
Schematic Design Progress
December 02, 2010